Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/html/wp-includes/functions.php on line 6260 Environmental Permitting Final for AV Solar Ranch One - Ink World Magazine
Flexible Electronics News

Environmental Permitting Final for AV Solar Ranch One

Construction is expected to begin in 2011, and the project to be completed by the end of 2013

First Solar, Inc. announced that the Environmental Impact Report for the 230MW AV Solar Ranch One photovoltaic solar project in Los Angeles County has become final and non-appealable.

This milestone occurred on Jan. 7, 2011, 30 days after the county Board of Supervisors unanimously rejected an appeal from an earlier decision of the Los Angeles Regional Planning Commission approving the conditional use permit and related environmental impact report for the project. Parties had 30 days from the Board of Supervisors action within which to initiate a lawsuit in Los Angeles Superior Court challenging the Board’s decision, pursuant to the California Environmental Quality Act. No legal actions were filed.

Construction is expected to begin in 2011, and the project to be completed by the end of 2013. During construction, the project will employ up to 400 workers.